Brisbane Airport Corporation · Airport Facilities

Low Voltage Distribution — Asset Management Plan

Assets in Scope
274 / 127 sites
Target Completion
30 Oct 2026
Illustrative Example Stage 2 · In Progress
Assets in Scope
274127 sites
MSB · MSSB · DB across the BNE estate
Condition Assessed
18869%
188 of 274 inspected to date
Assets At Risk
8230%
Condition grade 4–5 · renewal required
Immediate Safety Defects
11Action now
Live findings flagged for make-safe
Avg Condition Grade
2.95Mid-life
Weighted across inspected sample
Pre-AS3000:2018 Assets
71%Legacy
Predate current wiring / AS61439
20-yr CAPEX Forecast
$14.2MRenewal
$6.8M front-loaded in first 5 years
Annual OPEX
$0.42M/yr
Maintenance, testing & inspection

Condition Grade Distribution

Appendix B · 1–5 scale

Condition Confidence

Internal access governed by BAC live-work / isolation procedure. Boards not opened are graded "Assumed".

Programme

5 stages · 100%

Asset Mix by Type

Top Recurring Defects

% of inspected boards
Condition basis: Visual-only assessment per Appendix C proforma. Each asset graded 1 (Very Good) – 5 (Very Poor) with a condition-confidence flag (Inspected / Partially inspected / Assumed). Degradation profile and remaining useful life derived from grade, age, environment and work-order history. No electrical testing performed — follow-up testing program recommended separately.

Condition by Asset Type

stacked grade 1–5

Condition by Era Built

aging signal

Remaining Useful Life

Renewal demand horizon across the inspected population
RUL < 2 yrs
47Urgent
Plan renewal now
RUL 2–5 yrs
88Near-term
Programme into 5-yr CAPEX
RUL 5–10 yrs
96Mid-term
Monitor & maintain
RUL > 10 yrs
43Sound
Routine maintenance only

Grade Definitions

BAC condition grading scale — Appendix B
GradeConditionDescriptionCount% of sample

Risk Matrix

likelihood × consequence · count of assets
Low Medium High Extreme

Criticality Profile

service impact of failure
Critical assets (terminals, data centres, airside lighting reticulation) carry the highest consequence of failure. 18 grade 4–5 boards sit on critical supplies — these dominate the near-term capital priority.

Key Risk Themes

Systemic non-conformances driving the AMP recommendations
IDRisk / Non-conformanceDriverAssetsLikelihoodConsequenceRating
Ratings indicative, derived from visual inspection. RCD coverage, discrimination and arc-flash labelling accuracy require follow-up testing to confirm.
Rip & Replace
68$9.1M
Beyond economic refurbishment
Refurbish / Modify
95$3.6M
Safely upgrade in situ
Retain & Maintain
111$1.5M
Routine lifecycle only
Spare Capacity
38%Constrained
Boards able to accept new circuits

20-Year CAPEX Forecast

$M by year · renewal + upgrade
Rip & replaceRefurbish / modifyCompliance upgrade

5-Year Itemised Spend

detailed CAPEX + OPEX

Prioritised Capital Works

Top renewal candidates by risk-adjusted priority
PriorityAssetLocationTypeGradeRecommendationEst. costWindow
Asset ID Location / Building Type Built Grade Confidence RUL (yr) Criticality Recommendation
Showing a representative sample of the 274-asset inspection register. Full register delivered as native + PDF per the AMP submission schedule.
Stage 1 — Gap Analysis. Comparison of the 2015 AMP and current data against ISO 55001 and the BAC AMP template. Highlights missing information crucial to a defensible plan and value-add items for BAC consideration.
Data Complete
9
Information sets received & sufficient
Partial / Stale
6
Needs refresh or field verification
Critical Gaps
4
Blocking — RFI raised with BAC

Gap Register

Status vs ISO 55001 information requirements
Information setSourceStatusAMP impact
E3D-BAC-019-S · Stage sample

Sample Deliverables Pack

Open full document
A worked example of the Stage deliverable formats Empower3D would produce for the AMP — condition assessment proforma, asset register extract, risk register and capital works outputs. Illustrative content for demonstration.